Clark Design Build - Highland Hospital Acute Tower Replacement Project Rendering

Procurement

Schedule

Schedule

  • 1st & 2nd 2010 - Mobilization, Abatement, Shoring, Excavation, Demolition for Satellite Building
  • 1st & 2nd Qtr 2011 - Satellite Building
  • 2nd Qtr 2011 - Early Make-Ready Work: Mobilization, Abatement, Shoring, Excavation, Demolition for Acute Care Tower
  • 4th Qtr 2011 & 1st QTR 2012 - Acute Care Tower
  • 2015 - Demolition of H Building & New Courtyard

Recently Executed Contracts

  • Crown Masonry (Alameda) - Masonry (SAT) LBE
  • Kwan Wo (San Francisco) - Misc Metal (ACT) WBE

Tentative Contracts

  • George Family (Novato) - Acoustical Ceiling (SAT/ACT) SBE, WBE
  • Corbin Building/ISEC (Oakland) - Doors and Hardware(SAT/ACT ) LBE,SLBE,MBE

Upcoming Contract Opportunities

  • Metal Deck (ACT)
  • Roofing (SAT/ACT)
  • Thermal and Spayed Insulation (SAT/ACT)
  • Expansion Joint Control (SAT/ACT)

Core Subcontractors

ELECTRICAL
Cupertino Electric, Inc.
Contact: Ken Humphrey, email
tel. 415-970-3452

PLUMBING & MECHANICAL
F.W. Spencer & Son, Inc.
Contact: Steve Sandkohl, email
tel. 415 468-5000 X 3004

FIRE PROTECTION
Cosco Fire Protection
Contact: Phil Raya, email
tel. 925.455.2751

STRUCTURAL STEEL
Herrick
Contact: Jim Lynch, email
tel. 209-956-4751

EXTERIOR SKIN
C/S Erectors, Inc.
Contact: Jeff Badarello, email
tel. (925) 820-8113

DRYWALL
Performance Contracting, Inc. (PCI)
Contact: Victoria Bennett, email
tel. 510-715-9072